Vyncint Group was appointed to act as Pre-construction and Construction Manager by Kier Project Investment (KPI), whilst satisfying their client, London Borough of Enfield’s (LBE), aspirations.
Following the successful completion of Phase 1, where we delivered 26 units for KPI under a Development Agreement for LBE, we were asked to deliver the remainder of the scheme under a JCT Design and Build 2011.
Project: Parsonage D, Holtwhites Hill, Jasper Close, Tudor Crescent, Enfield/Kier Project Investment
Client: London Borough of Enfield
Value: Construction, £17 million/GDV, £25 million
Start Date: July 2018
Completion Date: March 2019
Delivery: Construction of 72 SIPS Panel Timber Frame apartments and houses.